Progress on the centre has been quite remarkable, due to the generosity of Christians worldwide, and to date funds have become available to keep up with the rate of building progress.
No loans have been needed and work has never been halted by a lack of funds.
A Time Line
2002 (March) Land obtained, paid in full.
2003 (November) Architects plans approved
2004 (September) Work starts!
2006 (June) Main Structure completed
Roof Fitted
Windows Installed
2007 (October) Main façade, floors completed. Electrical system installed.
2008 (March) contract for heating, water, air-conditioning, sewerage let. Ground floor façade worked on.